The "Standard" Project Timeline - Once Construction Begins
- Jamie Wallace, CKD
- Mar 24, 2023
- 1 min read
Updated: Mar 27, 2023
When it comes to interior design construction, nothing is standard! But we put together this timeline a general rule of thumb, to help you start planning for your interior design & construction project.
In this blog post, we'll explore the timeline of an average construction project. Each project is unique, and there are always different milestones to achieve. From laying the foundation to adding the finishing touches, each step in the process requires careful attention to detail and expertise.

It's important to trust your project to an experienced team who can navigate these potential roadblocks with ease. Let's take a closer look at the timeline of an average construction project and gain a better understanding of what to expect from start to finish.
Weeks 1-2
- Dust & floor protection 
- Demolition 
- Straighten & level framing 
- Sub-contractors rough-in - Plumbing 
- Electrical 
- Duct work 
 
Weeks 3-4
- Close in inspections 
- Install insulation 
- Insulation inspection 
- Hang and finish drywall 
- Sand and prime drywall 
Weeks 5-6
- Painting 
- Set cabinets 
- Measure for countertops, need range on site 
- Install flooring 
- Countertop fabrication 
Weeks 7-8
- Interior trim work 
- Install countertops, if laminate 
- Subs trim out electric and plumbing 
Weeks 9-10
- Countertop install, if solid surface or granite 
- Appliance install 
- Walk-through and punchlist 
Weeks 11-12
- Countertop install, if Cambria 
- Remaining appliance install, if awaiting Cambria 
- Cleaning, if approved by homeowners 
- Thank you and photos 
Conclusion
No two projects are alike, and yours will almost certainly vary from this schedule. It's also important to keep in mind that all projects are subject to contractor schedules, product deliveries, backorders, accidents, and delays. All the more reason to trust your project to an experienced pro!